Composite Rate Build Up – Upper Floor Concrete Slabs
The Elemental Estimate layout and grouping of items will be used in this example. When building up composite rates for Approximate Quantities, you have to follow some basic principles. We are going to illustrate a composite rate build-up for Upper Floor Concrete Slabs:
200m Thick solid reinforced concrete slabs for upper floor 25MPa, steel reinforcement 120kg/m3, rough formwork to soffits, striking off and floating the top surface, including plaster and paint to soffits. Ceramic floor tiles fixed with adhesive on 25mm screed.
Step 1
First, you have to determine the Group unit of measurement. When you are measuring Upper Floor Concrete Slabs in Elemental or Approximate Quantities estimating, the group unit of measurement is the square metre (m2).
Step 2
The second step is listing all associated Bill items that can be mapped to Upper Floor Slabs by area. These are:
- Reinforced concrete slab – (m3) Rate – R1500
- Steel reinforcement to slabs – (Tonne) Rate – R10,000.00
- Formwork to soffits – (m2) Rate – R175
- Striking off and floating top surface – (m2) Rate – R10
- Plaster to concrete soffits – (m2) Rate – R30
- Paint on plastered soffits – (m2) Rate – R30
- Ceramic floor tiles – (m2) Rate – R250
- Screeds – (m2) Rate – R30
Step 3
Since your Group unit is the square metre (m2), you should convert the Bill item rates to Cost per Square Metre.
Rate Build Up
GROUP – SLABS |
Rate – Cost Per Square Metre (m2) Rands | |
1m2 of Concrete slabs: | ||
200 x 1000 x 1000 | ||
0.2 x 1 x 1 = 0.2m3 | ||
0.2m3 x R1500 = R300 | 300 | |
1m2 of Steel reinforcement: | ||
Slabs reinforcement density value = 120kg/m3 | ||
200 x 1000 x 1000 | ||
0.2 x 1 x 1 = 0.2m3 | ||
0.2m3 x 120 =24kg = 0.024 tonnes | ||
0.024 ton x R10,000 = R240 | 240 | |
1m2 of Formwork to soffits: | ||
1m2 = R175 | 175 | |
1m2 Striking off and floating: | ||
1m2 = R10 | 10 | 725 |
1m2 Plaster to soffits: | ||
1m2 = R30 | 30 | |
1m2 Paint to soffits: | ||
1m2 = R30 | 30 | 60 |
1m2 Ceramic floor tiles: | ||
1m2 = R250 | 250 | |
1m2 Screeds: | ||
1m2 = R30 | 30 | 280 |
Composite Rate – SLABS | 1065 |
The composite rate for UPPER FLOOR SLABS is R1065 per square metre.
Elemental Layout and Grouping
Items which go into the element STRUCTURAL FRAME and component Slabs are stated in the description:
|
Unit | Quantity | Unit Rate | Cost/m2 | Subtotal | Cost | |
STRUCTURAL FRAME
|
|||||||
Slabs:
|
|||||||
200mm Solid reinforced concrete slab, steel reinforcement 120kg/m3, formwork to soffits, striking off and floating top surface.
|
M2 | 725 | |||||
Subtotal STRUCTURAL FRAME |
Items which go into the element FLOOR FINISHES and component Applied Floor Finishes are stated in the description:
|
Unit | Quantity | Unit Rate | Cost/m2 | Subtotal | Cost | |
FLOOR FINISHES
|
|||||||
Applied Floor Finishes:
|
|||||||
Allow a PC Sum of R150/m2 for Ceramic floor tiles fixed with adhesive on/and including 25mm screed. | M2 | 280 | |||||
Subtotal FLOOR FINISHES |
Items which go into the element CEILINGS AND SOFFITS and component Slab Soffit Finishes are stated in the description:
|
Unit | Quantity | Unit Rate | Cost/m2 | Subtotal | Cost | |
CEILINGS AND SOFFITS
|
|||||||
Slab Soffit Finishes:
|
|||||||
One coat cement plaster on concrete soffits and two coats Polvin Super Acrylic PVA paint plus undercoat, including preparing surfaces. | M2 | 60 | |||||
Subtotal CEILINGS AND SOFFITS |